Related individuals and politicians have participated in the construction of a gymnasium at a high school in Silistra

The construction of a new gymnasium at the “Atanas Burov” Economic High School in Silistra is nearing completion. The facility is being built as part of a European project valued at 15.5 million BGN, funded by the European Regional Development Fund and includes 15 vocational high schools in the regions of Varna, Dobrich, Silistra, and Shumen.

The commencement of activities at the Silistra school was announced by the school’s director, Denka Mihailova, with the public tender published in March 2024 for the project “Construction of a gymnasium as an extension to the building of the Professional High School of Agriculture and Food Industry ‘Atanas Burov’, Silistra.”

The estimated value of the public procurement is 1,243,647.66 BGN excluding VAT. Four companies participated in the announced tender: “Atlant 2013” LLC, “Ecoeffect 2018” LLC, “Stroiproject” LLC, and “Drastar Engineering” Ltd., managed by the recent favorite in local government construction contracts, Dimitar Nedjalkov.

A commission appointed by the school’s director, Denka Mihailova, allowed only one company—“Atlant 2013” LLC—to participate and review the bids, while the other three companies were disqualified. The main reason for disqualification was that the companies did not provide an adequate timeline for the activities and guarantees for completing the contract within the timeframe they specified in their bids.

Subsequently, one company—“Stroiproject”—challenged the procurement before the Commission for Protection of Competition (CPC). The commission ruled that there was no violation of the Public Procurement Act during the awarding process. Thus, the contract was concluded with the registered “Atlant 2013” LLC from Obzor for a value of 1,229,113.30 BGN excluding VAT. Construction activities began in the fall of 2024 and continue to this day.

However, several site visits conducted by “For the Truth” during the construction period revealed that the construction work was not being carried out by the company that won the public tender, “Atlant 2013” LLC, but by “Galaxy Stroy” Ltd.

The company “Galaxy Stroy” LLC is owned by municipal councilor Ivanaka Tasheva from the “Citizens for the Municipality” group in the Silistra municipal council. The company is registered under the name of Ms. Tasheva’s son, Galin Ivanov, but is effectively managed by her. She has also participated in other public tenders funded by European money in the municipality of Silistra. One of these was the renovation of blocks on Simeon Veliki Street in Silistra, which had the municipality as the client, involving the firms associated with the municipal councilor from DPS, Birol Mehmed, and the GERB activist Dimitar Nedjalkov.

Following an investigation by Za istinata (“For the Truth,”) the European Prosecutor’s Office launched an investigation due to suspicions of abuse and conflict of interest. When asked for a comment on why another company is actually executing the project, the school director, Ms. Denka Mihailova—who is also a municipal councilor from the GERB group in the Silistra municipal council—explained to “For the Truth” that the relationships and payments from the school as the contracting authority were only with the winning company “Atlant 2013” LLC, and the issue of which companies are actually executing the project was not under the contractor’s control during the construction.

After the conversation with Director Denka Mihailova, we were contacted by municipal councilor Ivanaka Tasheva. She explained that “Galaxy Stroy” Ltd. is indeed executing the project, but only for the “Architectural” part of it, which is the most significant. This was done based on a contract between “Atlant 2013” LLC and “Galaxy Stroy” Ltd.—the two companies have collaborated for a long time on other projects in Bulgaria.

Is this legal?

The Public Procurement Act allows other entities, different from the winning contractor, to be included in the execution. However, the use of subcontractors must be declared in the contractor’s bid, specifying what portion of the contract will be executed by them. Candidates and participants must indicate in their application or bid the subcontractors they intend to use and the share of the contract they will assign to them. In such cases, they must provide proof of the obligations undertaken by the subcontractors, as stated in Article 66, paragraph 1 of the Public Procurement Act (PPA). From the minutes of the conducted procedure, which is public, it is clear that the chosen company “Atlant 2013” LLC declared to the contracting authority that it would not assign any part of the contract to third parties. Thus, it was approved.

Subsequently, it turns out the opposite—most of the work is actually being performed by “Galaxy Stroy” Ltd., which, according to the contract with the official contractor, has been receiving a portion of the payments transferred by the school.

Although this involves European funds allocated through the state rather than municipal funds, the execution of public contracts by companies linked to municipal councilors, which are awarded by other councilors and local government representatives, naturally raises questions about their political connections and commitments. Moreover, the start of the project was preceded by a decision from the municipal council in March 2024 to approve the right to build an extension to the gymnasium. At that time, Mayor Alexander Sabanov urged the councilors to support the decision, stating: “Dear Mr. Chairman, dear ladies and gentlemen councilors, dear guests of today’s meeting, as some of you know, there is a project won for the construction of a gymnasium. So, I ask you to abstract from the fact that Ms. Denka Mihailova is the director of the school, she has won the tender, i.e., this is something good for the city. There is no need for politics in this report; overall, please support the proposal.”

However, the subsequent developments regarding the awarding and execution of the project suggest that political factors may have been at play. Ms. Tasheva participated in the voting and voted “in favor.” In this case, she certainly had a personal interest in the approval if she was aware that the company “Galaxy Stroy” Ltd. would be involved in the execution.

She does not hide her close relationships with certain municipal councilors from GERB party, and her group, “Citizens for the Municipality,” openly supported the GERB candidate in the runoff of the local elections in 2023.

All of this raises the question of whether the contractor “Atlant 2013” LLC was favored precisely because of its connection to the company “Galaxy Stroy” Ltd., which is doing a significant portion of the work, rather than for having the best offer.

Although the contractor won the bid because it proposed the best execution schedule, on January 6, 2025, an addendum was signed to the contract between the contracting authority and “Atlant 2013” LLC, extending the deadline for the completion of the gymnasium to March 7, 2025.

Истината струва скъпо. Ако сте я открили тук – подкрепете ни!

Най-четени разследвания

Още от автора

Medical supervision found no violations in Silistra cardiology, but does not want private partners

Medical services in invasive cardiology worth just over €1 million in 2025 and €522,000 in the first half of 2026 were carried out under a joint activity agreement...

“It’s not moral, but I supported it”: How Silistra councilors voted on a controversial deal with municipal property

At the latest meeting of the Silistra Municipal Council, a decision was adopted to exchange municipal property for privately owned property, with an additional payment. The deal sparked...

More and more farmers in Plovdiv region are giving up farming

Fruit and vegetable producers have taken to the streets across the country to protest against low farm-gate prices, a lack of market access and growing pressure from imported...

Още разследвания

Public procurement in Nedelino awarded to small firm, despite lack of competition

A nearly 1.7 million BGN (excluding VAT) public tender for the reconstruction and rehabilitation of the main street "Alexander Stamboliyski" in Nedelino has been awarded to the small...

“Captured Energy”: An insider reveals how the secret holding “Orion” owned by Hristo Kovachki controls the market

"Energy in Bulgaria is captured. And the owner of this captured energy is called Hristo Kovachki." With these words, former gas trading director at "Orion Holding" Veselin Todorov...

“Save Bedechka” Association: A deal with municipal properties deprives Stara Zagora of more than 500 thousand leva

The Municipal Council of Stara Zagora approved the exchange of municipal properties for lands in "Bedekka" Park, owned by "Esteti Homes" EOOD, a company owned by Evgeni Lishev....