Photo: Diyana Zhelyazkova
Nearly BGN 300,000 must be invested to restore the sports field at the school in Nikola Kozlevo, which has been in ruins for 10 years after renovation.
In 2014, the playground at the Tsanko Tserkovski Secondary School in Kozlevo was renovated at a cost of BGN 248,000 under the Growth and Sustainable Development of Regions program, financed by the state budget. The Ministry of Youth and Sports was the contracting authority for the construction, and the Sofia-based company Capitol Group was the contractor.
For the quarter of a million leva provided (at 2014 prices – ed.), the contractor was supposed to build a double multifunctional playground, including for mini-football, on a 40 by 20 meter site. The contract was signed in the summer of 2014, and construction was supposed to be completed within 60 calendar days. However, the expensive playground was never used by children because the flooring was destroyed after only one winter. “The builders were behind schedule, and in October and November, the cold weather set in, but they were in a hurry to finish because they had deadlines. They flooded the field with some kind of mixture, put up the fencing, and left,” recalls school principal Kitilian Kostadinov.
The playground couldn’t be used during the winter, and in April, when the students went out to play on it for the first time, the coating started to peel and flake off. The artificial surface wrinkled and became impossible to walk on, and the fencing began to tilt in the wind.
“We held exactly two classes on the new playground and then banned its use because it was dangerous for the children,”
explains Kostadinov.
At the end of 2015, the then GERB MP for Shumen, Ralitsa Todorova, submitted a question to the Ministry of Sport (MMS) about the condition of the pitch. “At present, due to poor workmanship, part of the flooring is swollen and detached, the soccer goals are not secured and safe, and the posts are tilted. This poses a danger to the children playing there, and the director has issued an order not to use the playground,” Todorova wrote, asking the MMS how the problem would be solved.
The ministry responds that “the project has been completed” and that a statement of completion has been signed, as well as a certificate of commissioning. Due to the delay in construction, the contractor has been fined BGN 3,300. An on-site inspection, ordered by the Minister of Sport on December 2, 2014, found poor-quality construction work, for which no payment had been made, the ministry said in its response to Ralitsa Todorova. Subsequently, the Ministry of Youth and Sports and the contractor are in court over the amount of compensation imposed, with the cases dragging on until 2023.
Over BGN 260,000 for a new mini-football pitch
The municipality of Nikola Kozlevo is now attempting to restore the ruined pitch and has commissioned a market valuation of the potential repairs in order to apply for the national program for shared financing of investment in sports facilities. The construction of a new mini-football pitch will cost BGN 264,000, according to data published in the electronic register of public procurement.
The sports field, measuring 40 by 20 meters, must first be cleared, which will cost BGN 13,000 (excluding VAT), according to bids from two companies.
The most expensive activity will be the installation of artificial turf, with a height of 4 centimeters, covering an area of 875 square meters, which will cost a total of BGN 61,000. The installation of geotextile will cost BGN 18,900, 27 metal fence posts will cost BGN 20,760, and a 4.5-meter-high polyethylene fence net will cost BGN 28,688. Sixty-three fence panels measuring 2.50 by 1.50 meters will cost over BGN 20,000. The installation of lightning protection will cost BGN 9,400. A metal structure for seats is planned to be built for BGN 1,050, and 150 seats will be installed, at BGN 45 each, for a total of BGN 6,750.
Thus, the final price of a new mini-football pitch will exceed BGN 264,000. A few years ago, this could have been done for BGN 40,000-50,000, but now the price exceeds BGN 200,000, according to builders.
The school principal hopes that funding for the sports field will be found after all. “There is no sports hall in Nikola Kozlevo, and young people want to use the school facilities. They constantly ask me if they can play in the school gym, but I am not allowed to give it to outsiders; only school teams can use it. That is why I hope we can build the outdoor playground so that all young people can play there,” says Kostadinov.