BG | EN

Public procurement worth €483,586 in Borino gets tangled between “€” and “BGN” and relies on repealed regulations

The three price offers are almost identical. ET “Khalil Veliev – Gyulfie Velieva” bid €483,586.50, while the other two companies offered just 50 cents more.

The evaluation report explains that the price per meal had already been predetermined by the managing authority. The fixed amount was €1.86 including VAT for each hot meal, plus another 7% for administrative, transport and storage costs.

The actual competition therefore came down to quality criteria. The factor carrying the greatest weight was the number of meat or fish main courses included in the weekly menu.

ET “Khalil Veliev – Gyulfie Velieva” offered five such meals a week. “Dzhedzho – 69” and “Kuzgun” each offered two. All three companies promised one dessert or piece of fruit per week.

The winning bidder received the maximum score of 100 points. The other two participants were both ranked second with 68.46 points. On 10 June, Mayor Mustafa Karaahmed selected ET “Khalil Veliev – Gyulfie Velieva” as the contractor.

The long-standing supplier remains at the table

The company is not a newcomer to the service. Public documents show that it has won contracts to provide hot meals in Borino since at least 2017. A contract was also signed with the company in 2019, while the ISUN system lists it as the contractor for the current “Hot Lunch” project as well.

Just seven days after the decision on the new tender, the company appeared again before the Municipal Council, though not in person, but through a proposal concerning a municipal property it rents.

On 17 June, the councillors extended the lease of 72 square metres on the first floor of Nikola Vaptsarov Secondary School to ET “Khalil Veliev – Gyulfie Velieva” for another five years. The new lease runs from 1 January 2027, with the rent set at €72 per month.

It is in this very school building that, according to the technical specifications, the hot meals are to be provided to beneficiaries from Borino.

Who reheated the paperwork?

The questions therefore extend beyond the content of the tender documents to the way they were checked and controlled.

Who reviewed the technical specifications before they were published?

Why does a procurement worth nearly half a million euros rely on repealed regulations?

And how many times can an old piece of text be reused before it starts to look like a new one?

Apparently, in Borino, the paperwork is served reheated too.

The difference is that the technical specifications explicitly prohibit reheating the food – but say nothing about reheating the procurement documents.

Истината струва скъпо. Ако сте я открили тук – подкрепете ни!

Най-четени: Още за новините

Още от автора

Nedelino Municipality announced an order for “Hot Lunch”, full of errors and absurdities

Nedelino Municipality has launched a €42,600 public procurement procedure, excluding VAT, for the supply of food products under the “Warm Lunch” project. But the tender documents appear to send...

Almost every second contract of the Municipality of Nedelino is concluded with a single offer

With only one bid submitted, 66 out of a total of 147 public procurement contracts awarded by Nedelino Municipality between October 2020 and July 2026 were signed. Their...

The mayor of Nedelino has a higher salary than the mayors of Plovdiv, Varna and Burgas

The mayor of Nedelino, Boyan Kehayov, declared BGN 114,848 in salary for 2025 — the highest among mayors in Smolyan Region. His income is 71% higher than the...

Още за новините

There is no money for repairs, but Dryanovo is looking for a contractor to restore the Kolyu Ficheto bridge

Dryanovo Municipality has launched a procedure to select a contractor to carry out repairs and conservation-restoration works on Kolyu Ficheto’s bridge over the Dryanovska River. The estimated value...

Almost every second contract of the Municipality of Nedelino is concluded with a single offer

With only one bid submitted, 66 out of a total of 147 public procurement contracts awarded by Nedelino Municipality between October 2020 and July 2026 were signed. Their...

Medical supervision found no violations in Silistra cardiology, but does not want private partners

Medical services in invasive cardiology worth just over €1 million in 2025 and €522,000 in the first half of 2026 were carried out under a joint activity agreement...